Duvon™ executed a single-day private tennis court retrofit using pre-fabricated mounting plates and pre-wired ProCourt heads — no civil work, no re-permitting.
This Newport Beach private installation called for a clean one-for-one luminaire swap on existing 35-foot poles. The owner needed a step-change in visual quality without civil work, planning amendments, or extended court closure.
We pre-fabricated the new mounting plates off-site so each pole could be swapped in under 90 minutes, and shipped the system as a fully wired kit. The installer crew completed the entire retrofit in a single working day. ProCourt 400W heads were aimed against the project's IES file using a digital inclinometer, and the system was commissioned the same evening.
Measured results: 47-fc average maintained, 1.25:1 uniformity, and zero spill onto the adjacent driveway and pool deck.
Highlights
Lighting Class: USTA Class II
Average Illuminance: 50 fc maintained horizontal
Uniformity: 1.25:1
Fixtures: ProCourt 400W LED Court Lights (5000K)
Energy Savings: Up to 62% vs HID